NEW QUESTION 1
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
- A. Cost baseline
- B. Cost forecasting
- C. Cost variance
- D. Cost budgeting
Answer: D
NEW QUESTION 2
Which of the following is used to illustrate the connections between work packages or activities and project team members?
- A. Hierarchical-type charts (HTC)
- B. Organizational breakdown structure (OBS)
- C. Work breakdown structure (WBS)
- D. Responsibility assignment matrix (RAM)
Answer: D
NEW QUESTION 3
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
- A. Authority
- B. Role
- C. Competency
- D. Responsibility
Answer: C
NEW QUESTION 4
An input to Conduct Procurements is:
- A. Independent estimates.
- B. Selected sellers.
- C. Seller proposals.
- D. Resource calendars.
Answer: C
NEW QUESTION 5
What is the definition of project plan execution?
- A. Integrating all planned activities
- B. Performing the activities included in the plan
- C. Developing and maintaining the plan
- D. Execution of deliverables
Answer: B
NEW QUESTION 6
Which of the following buffers protects the target finish date from slippage along the critical chain?
- A. Critical buffer
- B. Project buffer
- C. Duration buffer
- D. Feeding buffer
Answer: B
NEW QUESTION 7
Which of the following statements is true regarding project and product lifecycles?
- A. A single product lifecycle may consist of multiple project lifecycles.
- B. A product lifecycle is always shorter than the project lifecycle.
- C. A single product lifecycle can only have one project lifecycle.
- D. A single project lifecycle may consist of multiple product lifecycles.
Answer: A
NEW QUESTION 8
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
- A. Customers.
- B. Business partners.
- C. Sellers.
- D. Functional managers.
Answer: B
NEW QUESTION 9
What process determines which risks might affect the project?
- A. Qualitative risk analysis
- B. Identify Risks
- C. Plan Risk Management
- D. Quantitative risk analysis
Answer: B
NEW QUESTION 10
Which baselines make up the performance measurement baseline?
- A. Scope baseline, cost baseline, and schedule baseline
- B. Scope baseline, project management baseline, and quality baseline
- C. Cost baseline, schedule baseline, and risk baseline
- D. Cost baseline, project management baseline, and schedule baseline
Answer: A
NEW QUESTION 11
An example of a group decision-making technique is:
- A. nominal group technique
- B. majority
- C. affinity diagram
- D. multi-criteria decision analysis
Answer: A
NEW QUESTION 12
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
- A. Project Risk Management
- B. Project Human Resource Management
- C. Project Scope Management
- D. Project Stakeholder Management
Answer: D
NEW QUESTION 13
What is the function of a Project Management Office (PMO)?
- A. To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.
- B. To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.
- C. To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.
- D. To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.
Answer: A
NEW QUESTION 14
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
- A. Analogous
- B. Parametric
- C. Bottom-up
- D. Top-down
Answer: A
NEW QUESTION 15
Which process numerically analyzes the effect of identified risks on overall project objectives?
- A. Plan Risk Management
- B. Plan Risk Responses
- C. Perform Quantitative Risk Analysis
- D. Perform Qualitative Risk Analysis
Answer: C
NEW QUESTION 16
An input to the Perform Integrated Change Control process is:
- A. expert judgment
- B. seller proposals
- C. the project charter
- D. the project management plan
Answer: D
NEW QUESTION 17
Which tool or technique is effective in a project in which the deliverable is not a service or result?
- A. Inspection
- B. Variance analysis
- C. Decomposition
- D. Product analysis
Answer: D
NEW QUESTION 18
Which is a communication method used in the Report Performance process?
- A. Expert judgment
- B. Project management methodology
- C. Stakeholder analysis
- D. Status review meetings
Answer: D
NEW QUESTION 19
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
- A. Schedule network analysis
- B. Reserve analysis
- C. Alternative analysis
- D. Variance analysis
Answer: D
NEW QUESTION 20
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
- A. manager.
- B. success.
- C. deadline.
- D. scope.
Answer: B
NEW QUESTION 21
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
- A. Performance organizations
- B. Schedule baselines
- C. Work performance measurements
- D. Change requests
Answer: C
NEW QUESTION 22
......
Recommend!! Get the Full PMP dumps in VCE and PDF From Surepassexam, Welcome to Download: https://www.surepassexam.com/PMP-exam-dumps.html (New 918 Q&As Version)