Our pass rate is high to 98.9% and the similarity percentage between our PMP study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMP PMP exam in just one try? I am currently studying for the PMP PMP exam. Latest PMP PMP Test exam practice questions and answers, Try PMP PMP Brain Dumps First.

Online PMP free questions and answers of New Version:

NEW QUESTION 1

Activities on the critical path have which type of float?

  • A. Zero free float
  • B. Zero or negative float
  • C. Negative and positive float
  • D. Zero or positive float

Answer: B

NEW QUESTION 2

The three processes of Project Cost Management are:

  • A. Estimate Costs, Control Schedule, and Control Costs.
  • B. Estimate Costs, Determine Budget, and Estimate Activity Resources.
  • C. Determine Budget, Control Schedule, and Estimate Activity Resources.
  • D. Estimate Costs, Determine Budget, and Control Costs.

Answer: D

NEW QUESTION 3

Which tool or technique is used to develop the human resource management plan?

  • A. Ground rules
  • B. Expert judgment
  • C. Team-building activities
  • D. Interpersonal skills

Answer: B

NEW QUESTION 4

Scope, schedule, and cost parameters are integrated in the:

  • A. Performance measurement baseline.
  • B. Analysis of project forecasts,
  • C. Summary of changes approved in a period,
  • D. Analysis of past performance.

Answer: A

NEW QUESTION 5

The number of potential communication channels for a project with 5 stakeholders is:

  • A. 10.
  • B. 12.
  • C. 20.
  • D. 24.

Answer: A

NEW QUESTION 6

Which of the following is a strategy to deal with positive risks or opportunities?

  • A. Mitigate
  • B. Transfer
  • C. Exploit
  • D. Avoid

Answer: C

NEW QUESTION 7

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

  • A. stakeholder management strategy.
  • B. communications management plan,
  • C. stakeholder register,
  • D. performance report.

Answer: A

NEW QUESTION 8

Which tool or technique is used in Manage Stakeholder Expectations?

  • A. Stakeholder management strategy
  • B. Communication methods
  • C. Issue log
  • D. Change requests

Answer: B

NEW QUESTION 9

In the Plan Stakeholder Management process, expert judgment is used to:

  • A. Provide information needed to plan appropriate ways to engage project stakeholders.
  • B. Ensure comprehensive identification and listing of new stakeholders.
  • C. Analyze the information needed to develop the project scope statement.
  • D. Decide the level of engagement of the stakeholders at each required stage.

Answer: D

NEW QUESTION 10

Administer Procurements is part of which Process Group?

  • A. Planning
  • B. Executing
  • C. Monitoring and Controlling
  • D. Closing

Answer: C

NEW QUESTION 11

Which Process Group includes the Manage Stakeholder Engagement process?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Initiating

Answer: A

Explanation:
Reason: Control Stateholder Engagement is in the Monitoring and Control Process.

NEW QUESTION 12

Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables?

  • A. Estimate Activity Durations
  • B. Sequence Activities
  • C. Define Activities
  • D. Activity Attributes

Answer: C

NEW QUESTION 13

The following is a network diagram for a project.
PMP dumps exhibit
The shortest non-critical path for the project is how many days in duration?

  • A. 10
  • B. 12
  • C. 14
  • D. 16

Answer: A

NEW QUESTION 14

At the start of a typical project life cycle, costs are:

  • A. low, peak as work is carried out, and drop as the project nears the end.
  • B. low, become steady as work is carried out, and increase as the project nears the end.
  • C. high, drop as work is carried out, and increase as the project nears the end.
  • D. high, become low as work is carried out, and drop as the project nears the end.

Answer: A

NEW QUESTION 15

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

  • A. Collaboration
  • B. Negotiation
  • C. Decision making
  • D. Influencing

Answer: D

NEW QUESTION 16

The end point of a project phase can be referred to as:

  • A. project failure
  • B. closing process
  • C. stage gate
  • D. lifecycle

Answer: C

NEW QUESTION 17

How is quality control performed?

  • A. By identifying quality standards that are relevant to the project and determining how to satisfy them
  • B. By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed
  • C. By ensuring that the entire project team has been adequately trained in quality assurance processes
  • D. By applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards

Answer: B

NEW QUESTION 18

What is the primary benefit of meeting quality requirements?

  • A. Quality metrics
  • B. Less rework
  • C. Quality control measurements
  • D. Benchmarking

Answer: B

NEW QUESTION 19

An input of the Create WBS process is:

  • A. requirements documentation.
  • B. scope baseline.
  • C. project charter.
  • D. validated deliverables.

Answer: A

NEW QUESTION 20

Stakeholder satisfaction should be managed as a key project:

  • A. Benefit
  • B. Initiative
  • C. Objective
  • D. Process

Answer: C

NEW QUESTION 21

Inputs to the Define Activities process include:

  • A. Project scope statement, resource calendars, and work performance information.
  • B. Scope baseline, enterprise environmental factors, and organizational process assets.
  • C. Project scope statement, approved change requests, and WBS dictionary.
  • D. Scope baseline, enterprise environmental factors, and activity duration estimates.

Answer: B

NEW QUESTION 22
......

100% Valid and Newest Version PMP Questions & Answers shared by Certshared, Get Full Dumps HERE: https://www.certshared.com/exam/PMP/ (New 918 Q&As)