NEW QUESTION 1
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
- A. Project
- B. Functional
- C. Program
- D. Portfolio
Answer: D
NEW QUESTION 2
Plan Risk Management is the process of defining how to:
- A. Communicate identified risks to the project stakeholders.
- B. Conduct risk management activities for a project.
- C. Analyze the impact a specific risk may have on the project.
- D. Address unexpected risks that may occur during a projec
Answer: B
NEW QUESTION 3
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
- A. Identify Risks
- B. Perform Qualitative Risk Analysis
- C. Plan Risk Management
- D. Perform Quantitative Risk Analysis
Answer: B
NEW QUESTION 4
Which tools or techniques are used during the Close Project or Phase process?
- A. Reserve analysis and expert judgment
- B. Facilitation techniques and meetings
- C. Expert judgment and analytical techniques
- D. Performance reviews and meetings
Answer: C
NEW QUESTION 5
In which type of organizational structure are staff members grouped by specialty?
- A. Functional
- B. Projectized
- C. Matrix
- D. Balanced
Answer: A
NEW QUESTION 6
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
- A. Control chart
- B. Flowchart
- C. Run chart
- D. Pareto chart
Answer: B
NEW QUESTION 7
Which is a tool or technique used in Define Scope?
- A. Templates, forms, and standards
- B. Change requests
- C. Product analysis
- D. Project assumptions
Answer: C
NEW QUESTION 8
Which Project Time Management process includes bottom-up estimating as a tool or technique?
- A. Estimate Activity Resources
- B. Sequence Activities
- C. Estimate Activity Durations
- D. Develop Schedule
Answer: A
NEW QUESTION 9
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
- A. $50
- B. $100
- C. $125
- D. $175
Answer: C
NEW QUESTION 10
In complex projects/ initiating processes should be completed:
- A. Within a work package.
- B. In each phase of the project.
- C. To estimate schedule constraints.
- D. To estimate resource allocation
Answer: B
NEW QUESTION 11
Which process determines the risks that might affect the project?
- A. Perform Qualitative Risk Analysis
- B. Identify Risks
- C. Plan Risk Management
- D. Perform Quantitative Risk Analysis
Answer: B
NEW QUESTION 12
Cost baseline is an output of which of the following processes?
- A. Control Costs
- B. Determine Budget
- C. Estimate Costs
- D. Estimate Activity Resources
Answer: B
NEW QUESTION 13
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
- A. Business case
- B. Work breakdown structure
- C. Requirements documentation
- D. Risk register
Answer: C
NEW QUESTION 14
What is the primary benefit of meeting quality requirements?
- A. Quality metrics
- B. Less rework
- C. Quality control measurements
- D. Benchmarking
Answer: B
NEW QUESTION 15
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
- A. Timing
- B. Methodology
- C. Risk categories
- D. Budgeting
Answer: A
NEW QUESTION 16
Which is a communication method used in the Report Performance process?
- A. Expert judgment
- B. Project management methodology
- C. Stakeholder analysis
- D. Status review meetings
Answer: D
NEW QUESTION 17
Which project document is updated in the Control Stakeholder Engagement process?
- A. Project reports
- B. Issue log
- C. Lessons learned documentation
- D. Work performance information
Answer: B
NEW QUESTION 18
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
- A. Sensitivity analysis
- B. Three-point estimate
- C. Modeling and simulation
- D. Expected monetary value analysis
Answer: D
NEW QUESTION 19
Change requests are an output from which Project Integration Management process?
- A. Direct and Manage Project Execution
- B. Develop Project Management Plan
- C. Close Project
- D. Develop Project Charter
Answer: A
NEW QUESTION 20
Which Process Group and Knowledge Area include the Sequence Activities process?
- A. Executing Process Group and Project Time Management
- B. Executing Process Group and Project Cost Management
- C. Planning Process Group and Project Time Management
- D. Planning Process Group and Project Cost Management
Answer: C
NEW QUESTION 21
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
- A. Influencing
- B. Motivation
- C. Negotiation
- D. Trust building
Answer: B
NEW QUESTION 22
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
- A. Teaming
- B. Collective bargaining
- C. Sharing
- D. Working
Answer: A
NEW QUESTION 23
......