NEW QUESTION 1
In which Knowledge Area is the project charter developed?
- A. Project Cost Management
- B. Project Scope Management
- C. Project Time Management
- D. Project Integration Management
Answer: D
NEW QUESTION 2
Which items are an output of the Perform Integrated Change Control process?
- A. Work performance reports
- B. Accepted deliverables
- C. Project management plan updates
- D. Organizational process assets
Answer: C
NEW QUESTION 3
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
- A. Determine Budget.
- B. Baseline Budget.
- C. Control Costs.
- D. Estimate Cost
Answer: A
NEW QUESTION 4
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
- A. smooth/accommodate.
- B. force/direct,
- C. collaborate/problem solve,
- D. compromise/reconcil
Answer: C
NEW QUESTION 5
Risk exists the moment that a project is:
- A. planned.
- B. conceived.
- C. chartered.
- D. execute
Answer: B
NEW QUESTION 6
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:
- A. ends.
- B. begins.
- C. delays.
- D. deviate
Answer: A
NEW QUESTION 7
The staffing management plan is part of the:
- A. organizational process assets.
- B. resource calendar.
- C. human resource plan.
- D. Develop Project Team proces
Answer: C
NEW QUESTION 8
Which of the following is an output from Control Scope?
- A. Change requests
- B. Variance analysis
- C. Accepted deliverables
- D. Requirements documentation
Answer: A
NEW QUESTION 9
As the project progresses, which of the following is routinely collected from the project activities?
- A. Communication management activities
- B. Change requests
- C. Configuration verification and audit
- D. Work performance information
Answer: D
NEW QUESTION 10
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
- A. Scope plan
- B. Product scope
- C. Scope management plan
- D. Scope baseline
Answer: D
NEW QUESTION 11
The purpose of inspection in Perform Quality Control is to keep errors:
- A. in line with a measured degree of conformity.
- B. out of the hands of the customer.
- C. in a specified range of acceptable results.
- D. out of the proces
Answer: B
NEW QUESTION 12
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
- A. Timing
- B. Methodology
- C. Risk categories
- D. Budgeting
Answer: A
NEW QUESTION 13
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
- A. Control Scope
- B. Collect Requirements
- C. Create WBS
- D. Define Scope
Answer: B
NEW QUESTION 14
A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
- A. Historical information and the lessons-learned database.
- B. Historical information and the stakeholder register.
- C. Organizational process assets and the lessons-learned database.
- D. Project documents and historical informatio
Answer: A
NEW QUESTION 15
Change request status updates are an output of which process?
- A. Perform Integrated Change Control
- B. Direct and Manage Project Execution
- C. Close Project or Phase
- D. Monitor and Control Project Work
Answer: A
NEW QUESTION 16
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
- A. The influence of the stakeholders increases, the cost of changes increases.
- B. The influence of the stakeholders decreases, the cost of changes increases.
- C. The influence of the stakeholders increases, the cost of changes decreases.
- D. The influence of the stakeholders decreases, the cost of changes decrease
Answer: B
NEW QUESTION 17
In the Plan Stakeholder Management process, expert judgment is used to:
- A. Provide information needed to plan appropriate ways to engage project stakeholders.
- B. Ensure comprehensive identification and listing of new stakeholders.
- C. Analyze the information needed to develop the project scope statement.
- D. Decide the level of engagement of the stakeholders at each required stag
Answer: D
NEW QUESTION 18
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
- A. Level of control.
- B. Communication channels.
- C. Scope.
- D. Strategic alignmen