splitQ51. You are a project manager who uses Project Professional 2013. All resources in your project schedule have availability of 8 hours per day. You notice that several of the resources on the project are overallocated. You decide to level the project to help resolve the overallocations for the resources. Team members often do not work at the same time when completing their work on the task


74-343 | All About Real 74-343 braindumps

splitQ41. You manage a project by using Project Professional 2013. The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed. You need the work variance to be adjusted to reflect what has occurred during the performance of the task. What should you do? A. Adjust the value in the Baseline Work column. B. Enter a 0 in the remaining Dur